Anheuser-Busch - Can Line 40

Industrial Construction & Piping Systems

PMI was responsible for complete demolition of the existing Can Line 40 equipment and piping and installation of the new equipment and piping. Major equipment included pasteurizer, filler, bulk can de-palletizer, packer, various assorted conveyors, decline rinser, full case inspectors, ink and laser coders, case conveyor and diverter, accumulation tables, structural steel, platforms, staircases, seismic upgrades, and all associated piping and related mechanical control items.

Maintaining schedule and completion dates were critical to the project. Utilizing double shifts and extensive pre-planning and constant coordination, all milestone completion dates were successfully accomplished.

Owner & Engineer:
Anheuser-Busch

Duration:
5 months

Total Direct Man-Hours:
36,000