Chukchansi Gold Resort
Coarsegold, CA Phase 2, HVAC Wet SidePMI headed the second phase of expansion which included design, supply and installation of HVAC Wet Side Piping for the new eleven story Hotel and Casino.
- Engineer: Finnegan Erickson Associates
- Approximate Contract Amount: $1.9 Million
- Completion: August 2008
- Duration : 8 months
Contra Costa County
Pittsburg, CA East County CourthouseInstallation and piping of chillers boilers, pumps, and data center refrigeration piping.
- Approximate Contract Amount: $1 Million
- Completion: Ongoing