E&J Gallo, Livingston, CA
Piping to Tank Headers and Centrifuge Equipment
For this project, PMI field verified all equipment locations and structural steel. PMI procured materials, fabricated pipe, built new cellar tank headers, and installed new 4-inch lines to new centrifuge equipment. The project completed with a two-week shutdown where all lines had to be tied in.
Owner:
E&J Gallo
Engineer:
Eicheay Engineers Inc.
Duration:
4 months
Total Direct Man-Hours:
3,285