MillerCoors, Colfax, CA
Update Glycol System
PMI updated a glycol system, grading and excavating for new foundations. We set tanks and pumps, installed new glycol piping, and coordinated a shutdown to tie in the new glycol system to the existing system.
PMI also provided startup support.
Owner:
MillerCoors
Engineer:
Foth Production Solutions, LLC
Duration:
4 months
Total Direct Man-Hours:
1,067